Project: Stockton Waterfront Civic Buildings
Client: NHS
Main Contractor: Kier
Value: £2.4 million

This scheme we have been contracted to complete the Groundworkers for Kier Construction. The Package includes Pile cap and ground beams, internal concrete slabs and upstands, surface and foul drainage including attenuation tank, flow control and penstock installation as well as 2 nr NWL connections, external services and hard landscaping. 

 

The Challenge

Site Constrites, Offsite Car Parking, Water Management, Working alongside adjacent infrastructure works

Stockton Waterfront Civic Buildings

The Solution

Just in time deliveries, Working with local business to facilite offsite car parking, Overpumping into less time crictial excavations to allow offsite disposal, offsite connection completed out of hours, Open diaolog with adjacent construction

 

 

The Result

Foundations completed ontime, Reduced street parking to benefit local community, No delays / abortive works due to clash of working area

 

CGI Stockton Waterfront

Get in touch with us today

At Hewitson Ltd, we value your feedback and inquiries. Whether you have questions about our products, need support, or want to learn more about our services, our dedicated team is here to assist you. Please fill out the form below, and we will respond promptly. Alternatively, you can reach us via phone or email during our business hours. We look forward to connecting with you!

1 + 3 =

Head Office – Teesside Grange, Eaglescliffe, Stockton-on-Tees, TS16 0QH – Tel: 01642 786969

Tyne & Wear – Axis Building, Maingate Kingsway North, Gateshead, NE11 0NQ – Tel: 0191 404 6840