Project: Callerton Academy
Client: Department for Education
Main Contractor: Morgan Sindall Construction
Value: £7 Million

Following on from a successful relationship with Morgan Sindall Infrastructure, Callerton Academy was our first project working with Morgan Sindall Construction, the scheme is the full Groundworks Package for the construction of a new school, including Bulk Earthworks, Substructures , Retaining Walls, Ground bearing and Suspended Slabs, Drainage including diversion of NWL mains, Externals and Associated Services.

The Challenge

Budget Issues, Unpresidented Weather conditions, Live School Rescritions, Working in close proximy of residents

 

Stockton Waterfront Civic Buildings

The Solution

Fortnightly Forecasting, Proactive Drainage installation for catchment of water, Forward planning of deliveries due to restricted access to site, Resident engagement

 

 

The Result

Tailored costs for clients budgets, Minimal lose of working hours, Re-use of site won clays for fill, On programme with high quality of works.

Get in touch with us today

At Hewitson Ltd, we value your feedback and inquiries. Whether you have questions about our products, need support, or want to learn more about our services, our dedicated team is here to assist you. Please fill out the form below, and we will respond promptly. Alternatively, you can reach us via phone or email during our business hours. We look forward to connecting with you!

13 + 13 =

Head Office – Teesside Grange, Eaglescliffe, Stockton-on-Tees, TS16 0QH – Tel: 01642 786969

Tyne & Wear – Axis Building, Maingate Kingsway North, Gateshead, NE11 0NQ – Tel: 0191 404 6840